The City of Visalia’s Transit Operations & Maintenance facility underwent an expansion just shy of $2.3 million. As the facility acts as the maintenance hub for the City of Visalia’s transit busses, it was imperative that it remain operable during construction. For this reason, the project was divided into 11 phases to ensure it was running 24 hours a day, 7 days a week.
The expansion project consisted of a 6,497 square foot addition to the shop building, 1,633 square foot addition to the wash building and 1,029 square feet of new office space. Adding to the list, was 100,000 square feet of site improvements including a storm drain, water lines, electrical underground and site lighting, and approximately 98,000 square feet of new asphalt paving. In addition to Seals/Biehle’s general contracting services on the project, they also carried out the site and structural concrete, metal-stud framing, and the installation of drywall, doors and hardware.
|